COMPARATIVE ANALYSIS OF PLANNED AND ACTUAL DEADLINES AND BUDGETS FOR THE ROAD INFRASTRUCTURE PROJECTS
Abstract
Observing the planned deadlines and budgets for the road infrastructure projects is a rarity,
not only in the Republic of North Macedonia, but everywhere in the world. Such a situation
affects not only the participants of the projects, but also the community, because such projects
are mostly financed with public funds. Data on 24 road infrastructure projects in the Republic
of North Macedonia was collected and then analyzed through field research. As the main
reasons for extension of deadlines and changes in the foreseen budgets, the following were
detected: climate conditions, the occurrence of unforeseen works and surpluses, errors in the
project documentation, inadequate planning of the project realization, legal regulations,
communication between the participants and other influences. It is recommended that during
the construction of the road infrastructure, to pay attention to the following: initial and
continuous planning emphasizing the climate conditions, the quality of project documentation,
synchronization, implementation and control of activities by experienced personnel; timely
monitoring and application of the changes in the legal regulation, etc.
Authors
1. M. Sc. Milena Josifovska-Miloshevska 2. Prof. Dr. sc. Valentina Žileska Pančovska 3. Prof. Dr. sc. Goran Mijoski
1. M. Sc. Milena Josifovska-Miloshevska 2. Prof. Dr. sc. Valentina Žileska Pančovska 3. Prof. Dr. sc. Goran Mijoski
Keywords
Budget, construction, delay, construction deadline
Budget, construction, delay, construction deadline