DEFICIENCIES IN THE APPLICATION OF THE FIDIC YELLOW BOOK FOR CONTRACT CONDITIONS (DESIGN–BUILD SYSTEM) EXAMPLES OF ROAD CONSTRUCTION IN THE REPUBLIC OF SERBIA
Abstract
When the Investor has a finished project for the execution
of construction, a construction contract is signed with the
contractor (Red Book of FIDIC contract conditions). Due to
the age of the projects, errors in the projects themselves,
additional conditions of the holders of public authorization
during the execution of the construction, the contractor
submits a large number of variation warrants to the Investor
and thus increases the value of the project. Since this way of
contracting construction projects for the Investor presents
itself as a problem in financial planning, for the last few years,
the Investor has been contracting construction projects
according to the Yellow Book of FIDIC contracting conditions
(Design-Build system). This method of contracting, however,
creates new problems, such as: delays in the development of
projects, unfinished acquisition of land, delays in obtaining
a construction permit, introduction of the contractor to
the property, planning of the dynamics of the execution of
construction and others.
Authors
Milovan Ćeranić
Milovan Ćeranić
Keywords
FIDIC contract terms, project, Investor, variation warrants, dynamics of construction execution, construction permit, acquisition of land
FIDIC contract terms, project, Investor, variation warrants, dynamics of construction execution, construction permit, acquisition of land